Reno, Nev. (Nov. 18, 2026) – With the rapid proliferation of the digital realm and a growing artificial intelligence sector, data centers are spreading across the world. Nevada is one of the fastest-growing data center regions in the U.S. and globally due to abundant land, cost-competitive energy, and an attractive tax and regulatory environment. This explosive growth offers both opportunities and challenges due to the water and electricity required to operate these centers.
DRI scientists Erik Henzl and Sean McKenna produced a comprehensive report: Data Center Water and Electricity Consumption in Nevada to inform the public and policy makers about this rapidly growing sector of the state's economy. First published in early 2026, an updated appendix has been added to the report as of Nov. 18, 2026. The new appendix uses new information from NV Energy's 2026 Integrated Resource Plan to project the water and electricity needed to support future data center growth through 2036. According to Data Center Map , more than 75 data centers are currently in operation, under construction, or planned in Nevada.
"Nevada has the potential to be a central player in the increasingly digital world, but there are challenges that must be resolved to ensure that other stakeholders and priorities are balanced with the increasing demands of rapid data center expansion," said report author Sean McKenna, Senior Program Developer and Hydrologist at DRI.
The report offers estimates of water and electricity use that are calculated based on the size of proposed and under-construction data centers in the state and average resource use for existing and new technologies. The uncertainty around exact water and power usage remains a challenge for understanding their impact. Because the information is not available, the report does not include the resource use of Nevada's existing data centers.
Nevada's data center market has grown rapidly over just two years. Between 2024 and 2026, there has been a 180% increase in data center capacity requests and a 70% increase in data center load growth across the state. Data centers currently comprise just 5% of NV Energy's sales, but this number is expected to rise to 64% by 2046.
To put the state's data center growth in context, that is roughly equivalent to the state's net electricity generation in 2024, or the energy demand of 5 million homes. It is also nearly double the total energy required to power all electric and plug-in hybrid vehicles in the nation in 2025.
The water needed to support these new data centers is also examined, with estimates provided for both on-site, direct water use and the water required for their energy production. On-site water use is highly dependent on the cooling technology being used by each data center, and this information is not made available by the owners and operators. The report provides estimates based on available and emerging cooling technologies and their water efficiency. Despite the rapid growth of data centers in the state, advancements in cooling technologies result in a lower range of estimated direct water use than was provided in the initial report. However, the estimated water needed for electricity generation increases from the initial report, as driven by the large increase in the power required for new data centers. Direct water use for new data centers in the state by 2036 is estimated at approximately 12,770 acre feet, or 4 billion gallons, per year. The full range for this estimate is between 4,257 and 63,850 acre feet/year (between 1.4 and 20 billion gallons/year).
By 2036, DRI's estimate for the annual indirect water demand linked to Nevada's new data center power requirements is approximately 21,283 acre feet/year (roughly 7 billion gallons). This is roughly equivalent to the annual water use of 64,000 American households.